Lotte Chemical Titan plans maintenance at No. 2 cracker
Lotte Chemical Titan is likely to take its No. 2 naphtha cracker off-stream for a maintenance turnaround. The plant is expected to be taken off-stream in mid-February 2017. It is slated to remain shut f for a period of around 6 weeks. The cracker has an ethylene capacity of 435 kta and propylene capacity of 260 kta that is located in Pasir Gudang, Malaysia.
Date:
2016/12/22